The dismantling of the historic Elphinstone Road Over Bridge (ROB), a century-old structure built in 1913 during the British era, began on Friday as part of a broader infrastructure overhaul linked to the ambitious Sewri -Worli Elevated Connector project of MMRDA. The estimated cost of this Double Decker Bridge is Rs. 168 crore.
The completion period of the Railway portion is around 1 year after dismantling of existing ROB. According to sources, authorities are targeting to complete the dismantling and reconstruction work in two years.
Originally slated for completion within 20 days, the schedule has now been extended until July 10, 2025, due to constraints around railway traffic blocks. The dismantling of the approach roads — excluding the section directly above railway tracks — is expected to conclude by May 30, 2025.
This phase alone involves the removal of around 16,316 cubic meters of solid structures using heavy equipment, including two Poclain.
You may also like
Tension prevails in Jaipur after ruckus outside Jama Masjid, MLA booked
IPL 2025: CSK Will Work Very Hard On Every Game To Find Answers For Next Year, Says Fleming
Top 10 A24 movies of all time ranked - Lady Bird is only at No. 2
VE Day wasn't end of World War Two pain - but here's exactly why it is so special
Africa's hidden gem with the 'world's best beach' and £1.68 pints